$TTI The Arkansas bromine spend is contracted now, and the release never prices it. Note 6 of the 10-Q puts outstanding purchase and work order commitments for the plant at about 67.8 million dollars, plus 13.5 million dollars of power infrastructure commitments due over five years, on top of 46.7 million dollars of supply purchase obligations running through 2028.
Phase 2 mechanical completion is targeted by the end of 2026, with first production anticipated in early 2028.