$ATLX Recent sat image (I have old to compare)
1. Verified Project Progress: What is 100% Done
• DMS Processing Site Earthworks: Full clearing, grading, terracing, and pad compaction are complete on the main processing plot. The land is fully leveled to accept heavy engineering foundations.
• Infrastructure Access Corridors:
• The primary heavy haulage road flanking the western boundary is fully widened and operational to handle heavy machinery.
• The serpentine access tracks on the right quadrant are cut and established to provide a dedicated logistical corridor to the future Waste Pile 2 and tailings zones.
• Equipment Procurement & Logistics: The modular DMS processing plant has been fully paid for and delivered to Brazil. Critical plant parts, structures, and auxiliary equipment are staged in secure local yards.
• Contractor Mobilization: Civil and electromechanical crews are mobilized to begin foundation work and subsequent equipment assembly.